Guidelines for Examination
PART A
CHAPTER III EXAMINATION OF FORMAL REQUIREMENTS
12. Designation of Contracting States
12.5 Application deemed to be withdrawn
 

HOME

E  /  D   /  F

 

 
 
PART A
CHAPTER III EXAMINATION OF FORMAL REQUIREMENTSCHAPTER III EXAMINATION OF FORMAL REQUIREMENTS
12. Designation of Contracting States12. Designation of Contracting States
  12.4 Surcharge paid insufficient12.4 Surcharge paid insufficient     12.6 Request for Grant form12.6 Request for Grant form  
 

12.5

Application deemed to be withdrawn

 

Where no designation fee is validly paid by expiry of the periods of grace under Rule 85a, the application is deemed to be withdrawn; the surrender of one or more priority claims subsequent to this legal consequence does not alter the position.

 

Where the application is deemed to have been withdrawn because of failure to pay the designation fees, the loss of rights ensues on expiry of the normal period. Similarly, the deemed withdrawal of a designation of a Contracting State takes effect upon expiry of the normal period, and not upon expiry of the period of grace provided by Rule 85a (see G 4/98, OJ 3/2001, 131). The applicant is notified of the loss of rights only where, contrary to his originally declared intention in the Request for Grant form (Form 1001), he has failed to pay designation fees for States for which he had indicated his intention to pay.

 

Art. 79(3)

Art. 91(4)

Rule 69(1)



Re-establishment of rights in respect of the periods under Art. 79(2) and Rule 85a is excluded under Art. 122(5) (see J 12/82, OJ 6/1983, 221).

 

Art. 122(5)